NEW QUESTION 36
What can influence the Product Availability Check during the creation of a sales order? Note: There are 2 correct answers to this question.

  • A. The customer
  • B. The material
  • C. The customer material info record
  • D. The plant

Answer: A,C

 

NEW QUESTION 37
You test the various options that SAP S/4HANA Cloud offers for stock transfers between two different plants within the same company code. Which special features do stock transport orders have? Note: There are 2 correct answers to this question.

  • A. The material on the road is part of the valuated stock of the shipping plant.
  • B. The material on the road is managed in the stock in transit of the receiving plant.
  • C. You can optionally post the goods issue from inspection stock in the supplying plant.
  • D. If necessary, you can post the goods receipt to blocked stock in the receiving plant.

Answer: B,D

 

NEW QUESTION 38
What determines the set of data migration objects available from the Migrate Your Data application?

  • A. The selected target fields
  • B. The selected business scenarios
  • C. The selected source system
  • D. The customer legacy system

Answer: B

 

NEW QUESTION 39
What are the available methods through which you can fill staging tables in the SAP HANA database of the target system? Note: There are 3 correct answers to this question.

  • A. Customer's ETL tools
  • B. SAP SQL Anywhere
  • C. XML templates
  • D. SAP HANA Smart Data Integration (SDI)
  • E. SAP Smart Data Access

Answer: A,C,D

 

NEW QUESTION 40
Which technology is used to integrate SAP S/4HANA Cloud with other SAP and non-SAP applications?

  • A. Direct connectivity
  • B. SAP Landscape Transformation Replication Server
  • C. SQLConnect function
  • D. SAP Change and Transport System

Answer: A

 

NEW QUESTION 41
Which of the following is a prerequisite for using Automated Receipt Settlement (ERS) in a procurement process? Note: There are 2 correct answers to this question.

  • A. The indicator for ERS is set in the purchasing info record.
  • B. The indicator for ERS is set in the supplier master record.
  • C. The indicator for ERS is set in the purchase order item.
  • D. The indicator for ERS is set in the material master record.

Answer: B,C

 

NEW QUESTION 42
How are analytics capabilities built into SAP S/4HANA Cloud?

  • A. They are installed on a dedicated SAP Fiori frontend server
  • B. They are embedded in the same technical stack as the application
  • C. They are extended by the user to a dedicated SAP Fiori frontend server
  • D. They are installed as an add-on to the application

Answer: B

 

NEW QUESTION 43
What are features of the Stock Transfer without Delivery (BMH) scope item? Note: There are 2 correct answers to this question.

  • A. You can monitor stock in transit
  • B. You can maintain shipping data manually
  • C. You can transfer quality inspection stock
  • D. You can enter planned delivery costs

Answer: A,D

 

NEW QUESTION 44
When can you add relationships in the organizational structure in SAP Central Business Configuration? Note: There are 2 correct answers to this question.

  • A. Before initial content activation
  • B. Before defining the primary finance settings
  • C. After content activation
  • D. During content activation

Answer: A,C

 

NEW QUESTION 45
You want to manually record an initial entry of stock for a material. You should be able to enter both a quantity and an amount. How do you proceed?

  • A. Use the Enter Inventory Count app
  • B. Use the Manage Stock app
  • C. Use the Post Goods Movement app
  • D. Use the Post Goods Receipt without Reference app

Answer: C

 

NEW QUESTION 46
How is the productive system configured? Note: There are 2 correct answers to this question.

  • A. Through Central Business Configuration (CBC) in SAP Business Technology Platform
  • B. Through the Solution Documentation component of the SAP Solution Manager
  • C. Via the Cloud Application Lifecycle Management (CALM) Implementation Portal
  • D. Through transports from the quality system

Answer: B,C

 

NEW QUESTION 47
Which of the following tasks can you perform using the Post Goods Movement (MIGO) app? Note: There are 3 correct answers to this question.

  • A. Post a component backflush
  • B. Create a material reservation
  • C. Search for purchase orders
  • D. Display a material document
  • E. Post a stock transfer between two plants

Answer: C,D,E

 

NEW QUESTION 48
When configuring the Product Availability Check, which of the following can you decide to exclude from the available stock? Note: There are 3 correct answers to this question.

  • A. Subcontractor Stock
  • B. Unrestricted-Use Own Stock
  • C. Unrestricted-Use Supplier Consignment Stock
  • D. Blocked Own Stock
  • E. Stock in Transfer

Answer: A,D,E

 

NEW QUESTION 49
Which characteristics apply to a shipping point? Note: There are 2 correct answers to this question.

  • A. A shipping point is stored at sales order header level.
  • B. Several shipping points can be assigned to one plant.
  • C. A shipping point is assigned to exactly one plant.
  • D. A shipping point is determined when the sales order is created.

Answer: B,D

 

NEW QUESTION 50
Which resources do you use when planning a Fit-to-Standard workshop? Note: There are 2 correct answers to this question.

  • A. Legacy system configurations
  • B. Business process test automates
  • C. Business process flows
  • D. Test scripts

Answer: C,D

 

NEW QUESTION 51
What is one purpose of the Supply Protection (SUP) feature?

  • A. Reserve quantities for a category of customers
  • B. Protect yourself from unreliable suppliers
  • C. Sell products in the sequence of incoming customer orders
  • D. Propose framework agreements with suppliers to secure supply quantities

Answer: A

 

NEW QUESTION 52
Which organizational units are directly linked to a plant? Note: There are 2 correct answers to this question.

  • A. Storage location
  • B. Sales office
  • C. Company code
  • D. Credit control area

Answer: A,C

 

NEW QUESTION 53
In which implementation phase do you perform data load preparation?

  • A. Explore
  • B. Prepare
  • C. Deploy
  • D. Realize

Answer: A

 

NEW QUESTION 54
In a subcontracting process, in which process step does the consumption posting of the components take place?

  • A. Creation of subcontracting purchase order
  • B. Stock transfer to subcontracting stock
  • C. Goods receipt for subcontracting purchase order
  • D. Invoice receipt for subcontracting purchase order

Answer: C

 

NEW QUESTION 55
What can you identify with the Top-Down and Bottom-Up Analysis in the Batch Information Cockpit? Note: There are 2 correct answers to this question.

  • A. Which batch managed materials are purchased from which supplier
  • B. Which batches are delivered from which distribution center
  • C. Which batches are delivered to which customer
  • D. Which raw material batches are used to produce which finished product

Answer: C,D

 

NEW QUESTION 56
What is the purpose of the Starter system in the SAP S/4HANA Cloud implementation project?

  • A. To configure the customer's personalized solution for demonstration and testing during the Realize phase
  • B. To conduct a blueprint workshop to identify all customer requirements for a completely customized solution
  • C. To demonstrate the customer's personalized solution, including process flows, the organizational structure, and authorizations
  • D. To demonstrate SAP Best Practices processes in a preconfigured system and identify customer personalization requirements

Answer: D

 

NEW QUESTION 57
In case of a delivery without reference to a sales order, what are the prerequisites for a successful batch determination? Note: There are 2 correct answers to this question.

  • A. Assign a default order type to the delivery item category
  • B. Assign the delivery type to a batch search procedure
  • C. Assign a default order type to the delivery type
  • D. Assign the default order type to a batch search procedure

Answer: C,D

 

NEW QUESTION 58
Which steps are required for data load preparation? Note: There are 3 correct answers to this question.

  • A. Perform full data load to determine the required loading times
  • B. Determine if public or private cloud is required for data migration
  • C. Review data load templates and determine data mapping
  • D. Determine data requirements based on scenario reviews
  • E. Design programs or reports required to extract data and initiate data cleansing

Answer: C,D,E

 

NEW QUESTION 59
In which task is the preliminary configuration information gathered to help the configuration experts gain insight into the customer's current processes?

  • A. Digital Discovery Assessment
  • B. Business Driven Configuration Assessment
  • C. Fit-to-Standard Workshops
  • D. Solution Definition

Answer: B

 

NEW QUESTION 60
......