Which of the following efforts can be minimized using the KANBAN procedure?
Correct Answer: A
Vote an answer
Which of the following master data can be used with process orders? (Choose three)
Correct Answer: A,B,E
Vote an answer
You want to use the function "Read PP master data" in the production order. However, while calling the function you receive an error message.
What could be the reason?
What could be the reason?
Correct Answer: D
Vote an answer
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?
What do you have to consider in this scenario?
Correct Answer: A
Vote an answer
You want to send production order-related data like confirmations, goods receipts, goods issues, and other user-specific actual data from an external process control system to SAP ECC.
How can you fulfill this requirement?
How can you fulfill this requirement?
Correct Answer: B
Vote an answer
Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.
How is the resulting firming interval specified in this scenario?
How is the resulting firming interval specified in this scenario?
Correct Answer: A
Vote an answer
Which of the following statements about ATP (Available To Promise) checks for material components are correct? (Choose two)
Correct Answer: B,C
Vote an answer