Where in the SAP ECC system can you define production versions?
Correct Answer: A
Vote an answer
During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system.
Which of the following procurement type properties are valid? (Choose two)
Which of the following procurement type properties are valid? (Choose two)
Correct Answer: B,C
Vote an answer
You want to enhance the system statuses of a production order with user statuses.
How do you do this?
How do you do this?
Correct Answer: B
Vote an answer
Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)
Correct Answer: A,B,E
Vote an answer
Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.
Which BOM item category must you set to fulfill this requirement?
Which BOM item category must you set to fulfill this requirement?
Correct Answer: D
Vote an answer
What data can be posted directly via the Plant Data Collection (PP-PDC) interface?
Correct Answer: D
Vote an answer
What option for selecting a routing exists when creating a production order?
Correct Answer: C
Vote an answer
In which master data object do you set the standard values for an operation?
Correct Answer: B
Vote an answer