A company uses Dynamics 365 Supply Chain Management.
Products must automatically be classified based on the company's objectives and priorities.
You need to create the ABC model.
Which three ABC codes should you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Products must automatically be classified based on the company's objectives and priorities.
You need to create the ABC model.
Which three ABC codes should you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Correct Answer: A,D,E
Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
A company is implementing Dynamics 365 Supply Chain Management. The company plans to use the Asset management module to manage equipment. The company must be able to perform the following activities:
* Track the operational status of each asset throughout its lifespan.
* View the current state of any asset at any time.
The system must restrict users from skipping states or resetting the status to an earlier state. You need to configure the system.
Solution: Configure asset lifecycle states and set the assets as Active. Does the solution meet the goal?
* Track the operational status of each asset throughout its lifespan.
* View the current state of any asset at any time.
The system must restrict users from skipping states or resetting the status to an earlier state. You need to configure the system.
Solution: Configure asset lifecycle states and set the assets as Active. Does the solution meet the goal?
Correct Answer: A
Vote an answer
A manufacturing company is implementing Dynamics 365 Supply Chain Management for asset maintenance.
The temperature control system requires calibration every six months by a certified metrologist.
You need to configure the six-month cadence requirement. What should you configure?
The temperature control system requires calibration every six months by a certified metrologist.
You need to configure the six-month cadence requirement. What should you configure?
Correct Answer: C
Vote an answer
A company uses Dynamics 365 Supply Chain Management to manage procurement operations.
The company plans to source some product lines from offshore vendors. The company wants to use the landed cost module feature for the shipment tracking and item costing.
You need to configure the procurement requirements.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

The company plans to source some product lines from offshore vendors. The company wants to use the landed cost module feature for the shipment tracking and item costing.
You need to configure the procurement requirements.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Correct Answer:

Explanation:

You need to configure settlement reports for the finance team.
Which processes should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Which processes should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Correct Answer:

Explanation:

A company uses Dynamics 365 Supply Chain Management to manage procurement operations.
The company plans to source some product lines from offshore vendors. The company wants to use the landed cost module feature for the shipment tracking and item costing.
You need to configure the landed cost functionality.
What should you configure for each requirement? To answer, drag the appropriate components to the correct requirements. Each component may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

The company plans to source some product lines from offshore vendors. The company wants to use the landed cost module feature for the shipment tracking and item costing.
You need to configure the landed cost functionality.
What should you configure for each requirement? To answer, drag the appropriate components to the correct requirements. Each component may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

Correct Answer:

Explanation:

A company discovers that planned costs are being calculated incorrectly due to missing configurations.
You need to configure the system to prevent calculation of the planned cost for items that are missing the following:
* a valid bill of materials (BOM) version
* a valid cost price
In which two locations can you configure the validation?
Select all answers that apply.
You need to configure the system to prevent calculation of the planned cost for items that are missing the following:
* a valid bill of materials (BOM) version
* a valid cost price
In which two locations can you configure the validation?
Select all answers that apply.
Correct Answer: E
Vote an answer
You are a functional consultant for a company named Contoso Entertainment System USA (USMF).
You need to copy the bill of materials (BOM) of item number T0012 to a new BOM.
To complete this task, sign in to Dynamics 365 portal.
You need to copy the bill of materials (BOM) of item number T0012 to a new BOM.
To complete this task, sign in to Dynamics 365 portal.
Correct Answer:
See explanation below.
Explanation:
Open item number T0012.
Go to Engineer > BOM > Lines and select the BOM for the item.
Click on Create BOM.
Select the Copy option.
Ensure the Add option is selected to create a new BOM rather than overwrite the existing BOM.
Click OK.
Explanation:
Open item number T0012.
Go to Engineer > BOM > Lines and select the BOM for the item.
Click on Create BOM.
Select the Copy option.
Ensure the Add option is selected to create a new BOM rather than overwrite the existing BOM.
Click OK.
A manufacturing company is using Dynamics 365 Supply Chain Management and wants to take advantage of the asset management capabilities.
The company has a fleet of delivery trucks and wants to maintain the trucks to maximize the vehicle ' s performance and lifespan while minimizing the risk of breakdowns. To meet these requirements, the asset maintenance plan for the trucks should be configured with the following:
* Require an oil change every 25,000 miles.
* Require a comprehensive inspection every six months.
You need to determine how to configure the asset maintenance plan lines for the delivery trucks.
How should you configure the maintenance plan line? To answer, move the appropriate plan type to the correct requirement. You may use each plan type once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

The company has a fleet of delivery trucks and wants to maintain the trucks to maximize the vehicle ' s performance and lifespan while minimizing the risk of breakdowns. To meet these requirements, the asset maintenance plan for the trucks should be configured with the following:
* Require an oil change every 25,000 miles.
* Require a comprehensive inspection every six months.
You need to determine how to configure the asset maintenance plan lines for the delivery trucks.
How should you configure the maintenance plan line? To answer, move the appropriate plan type to the correct requirement. You may use each plan type once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

Correct Answer:

Explanation:

A company uses Dynamics 365 Supply Chain Management for its operations in its primary distribution center. The company is opening a second warehouse for its e-commerce operations.
The second warehouse requires only half of the warehouse operations on the mobile device that the primary distribution center uses.
Several workers from the primary distribution center will help open the new warehouse alongside new workers. The primary distribution center workers will still work in the existing distribution center at times but need to default their warehouse menu to the new warehouse menu when they log in.
You need to configure the warehouse menus.
Which configurations should you use? To answer, move the appropriate forms to the correct requirements.
You may use each form once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

The second warehouse requires only half of the warehouse operations on the mobile device that the primary distribution center uses.
Several workers from the primary distribution center will help open the new warehouse alongside new workers. The primary distribution center workers will still work in the existing distribution center at times but need to default their warehouse menu to the new warehouse menu when they log in.
You need to configure the warehouse menus.
Which configurations should you use? To answer, move the appropriate forms to the correct requirements.
You may use each form once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

Correct Answer:

Explanation:

A company uses Dynamics 365 Supply Chain Management to manage procurement operations.
A purchasing clerk must process a purchasing request from an offshore vendor with the landed cost.
You need to explain the steps needed to perform this process
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions To the answer area and arrange them in the correct order.

A purchasing clerk must process a purchasing request from an offshore vendor with the landed cost.
You need to explain the steps needed to perform this process
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions To the answer area and arrange them in the correct order.

Correct Answer:

Explanation:

A company is implementing sales order functionality in Dynamics 365 for Finance and Operations.
The company has a business requirement to fulfill sales orders by using direct delivery.
You need to enter a direct delivery sales order so that a purchase order is automatically created.
What should you do after you enter the sales order and lines?
The company has a business requirement to fulfill sales orders by using direct delivery.
You need to enter a direct delivery sales order so that a purchase order is automatically created.
What should you do after you enter the sales order and lines?
Correct Answer: D
Vote an answer
You need to process the expedited photocopier replacement.
What should you do?
What should you do?
Correct Answer: C
Vote an answer