An integrator is installing three Synergy frames in different locations for a customer. As part of the installation, the customer requests a single monitoring dashboard that shows the current hardware status, warranty status, and open support cases of all three frames.
Which configuration steps must the integrator perform to provide the customer with this functionality?
Correct Answer: A Vote an answer
A customer wants to expand their existing cluster using the Grow Cluster functionality from OneView for vCenter Server.
Which OS build plan managed by HPE OneView for vCenter Server can the customer use?
Correct Answer: A Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
An integrator needs to re-deploy a specific firmware component to one of the Synergy compute nodes.
Click on the option that will allow an integrator to rewrite existing firmware components with the same option.
Correct Answer:
Refer to the exhibit.

How should an integrator pair interconnect bays to set up redundant fabrics in an HPE Synergy 12000 Frame?
Correct Answer: B Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
A customer needs to deploy a farm of Windows Server 2019 Hyper-V using an Image Streamer. The customer discovered that the OS Build Plan for this OS is not available from the Image Streamer interface.
How can the customer access all the tools and scripts needed to provision the required operating system?
Correct Answer: A Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
Which management tool required by HPE Infosight must be deployed at the customer site?
Correct Answer: C Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
Using SSMC, an integrator has added a new CPG on the HPE 3PAR StoreServ array integrated with HPE Composer.
The new CPG is not visible in the HPE Composer.
What must the integrator do to see the new CPG in the HPE Composer console?
Correct Answer: A Vote an answer
A customer needs to aggregate uplink ports from two Virtual Connect interconnects to increase bandwidth and availability of the networks configured for HPE Synergy platform.
Which steps must the integrator perform in the configuration to meet the customer's needs?
Correct Answer: A Vote an answer
An integrator needs to enable automatic support case logging for hardware incidents as part of a new Synergy installation.
Which configuration steps should the integrator perform to enable support case creation for the frame and all compute nodes?
Correct Answer: C Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
Refer to the exhibit.

A customer with a 3-frame Synergy composable infrastructure has received a second rack to expand existing composable infrastructure resource pools. The integrator has cabled the management ring as shown.
Which steps should the integrator take to increase availability of this configuration (Choose two.)
Correct Answer: A,C Vote an answer