
(May-2023) L4M3 Exam Dumps Contains FREE Real Quesions from the Actual Exam
Free Test Engine Verified By CIPS Certifications Certified Experts
NEW QUESTION # 44
Which of the following is the reason why liquidated damage clauses are embedded into a contract?
- A. To penalise the supplier for their wrongdoing
- B. To avoid argument on correct measure of damage
- C. Because compensation will be awarded immediately
- D. Because liquidated damages are the only remedy
Answer: B
Explanation:
Liquidated damages are an amount of money, agreed upon by the parties at the time of the contract signing, that establishes the damages that can be recovered in the event a party breaches the contract. The amount is supposed to reflect the best estimate of actual damages when the parties sign the contract. These usually apply to a specific type of breach, and in construction, it is frequently the failure to complete work on time.
Liquidated damages clauses are usually written as some sort of formula, for example:
Total Contract Price - [(X amount of $ per day) x (number of days late)] Including a liquidated damages clause can provide many benefits, the most important of which is predictability. When setting a predetermined amount of damages, it allows both parties a chance to negotiate and settle on a number they both feel is fair and reasonable.
From the owner's perspective, this acts like a cheap form of insurance against your contractors. In the event of a breach, the owner can immediately calculate the damages without going through the trouble of proving actual damages. Proving actual damages can be a complicated, lengthy, and costly process.
From a contractor perspective, this allows them to analyze the level of risk involved, and schedule appropriately. It also allows them the opportunity to limit the damage claims of the owner.
Reference:
- Construction Contract Clauses: What Is a Liquidated Damages Clause?
- CIPS study guide page 158-159
LO 3, AC 3.2
NEW QUESTION # 45
Under general legal principles of contract formation, which of the following will always automatically result in the termination of an offer?
1. Negotiation
2. Rejection
3. Failure conditionality
4. Non-disclosure
- A. 1 and 2 only
- B. 3 and 4 only
- C. 2 and 3 only
- D. 1 and 4 only
Answer: C
Explanation:
There are a number of ways for an offer to be terminated. They are events that may occur after an offer has been made which bring it to an end so that it can no longer be accepted. An offer is terminated in the following circumstances:
1. Revocation
2. Rejection
3. Lapse of time
4. Conditional Offer (or Failure of Conditionality)
5. Operation of law
6. Death
7. Acceptance
8. Illegality
Reference:
- How Is an Offer Terminated?
- CIPS study guide page 31-32
LO 1, AC 1.2
NEW QUESTION # 46
Which of the following is a true statement on express and implied terms?
- A. Express terms must be prepared by the party with expert knowledge
- B. Express terms always take precedent over implied terms
- C. Implied terms may derive from oral negotiations
- D. Express terms must always be in writing
Answer: C
Explanation:
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties.
Implied terms are terms implied into the contract by the courts. They are not expressly set out in the contract but are taken to be as effective as if they were and as if they had been included from day one of the contract. The express terms and any implied terms together create the legally binding obligations on the parties.
The types of express terms to be found in a contract are many and varied and will depend on the type of contract. Any term written into the contract is an express term and may refer to price, time scales, warranties and indemnities, limitations on liability, conditions precedent and so on.
An implied term is a term which the courts imply into a contract because it has not been expressly included by the parties. This may be because the parties did not consider it, did not think that any problem would arise in relation to it or simply omitted to include it.
The courts are very reluctant to imply terms into contracts and will only do so in the following circumstances:
1. terms implied under statute
2. terms implied under common law
3. terms implied because of custom or usage
4. terms implied due to previous dealings
5. terms implied 'in fact' or to reflect the parties' intentions
Reference:
- CIPS study guide page 126-132
- Contracts: Express and Implied Terms
LO 3, AC 3.1
NEW QUESTION # 47
What is the pricing method that incentivises the supplier to control their costs?
- A. Penetration pricing
- B. Skimming pricing
- C. Target Costing
- D. Cost-plus pricing
Answer: C
Explanation:
Penetration pricing is a marketing strategy used by businesses to attract customers to a new product or service by offering a lower price during its initial offering. The lower price helps a new product or service penetrate the market and attract customers away from competitors.
Price skimming is a product pricing strategy by which a firm charges the highest initial price that customers will pay and then lowers it over time. As the demand of the first customers is satisfied and competition enters the market, the firm lowers the price to attract another, more price-sensitive segment of the population. The skimming strategy gets its name from "skimming" successive layers of cream, or customer segments, as prices are lowered over time.
Incentive contracts allow sharing of the risks between the contractor and the client. The contractor is reimbursed all its justifiable costs in addition to a calculated fee. Target costing is an element of incentive contracts.
Cost-plus pricing is also known as markup pricing. It's a pricing method where a fixed percentage is added on top of the cost to produce Reference:
LO 3, AC 3.3
NEW QUESTION # 48
Transformers & Rectifiers Ltd wanted to buy some specialist gaskets. They sent a request for quotation with specification to Needs Ltd. The supplier replied with a quotation in which had its own terms and conditions. The buyer edited delivery terms on the quotation and sent the document back to Needs Ltd. Gaskets were delivered to Transformers' premise with an invoice from Needs Ltd. Which of the following is most likely to be the governing terms if the two companies must settle the dispute at court?
- A. Terms & conditions in the original quotation
- B. Edited terms and conditions
- C. Terms and conditions in the invoice
- D. Terms and conditions in the request for quotation
Answer: B
Explanation:
In the 'battle of the forms', generally who shot the last will win. This is not applied to this case. Initial RFQ is an invitation to treat, then the quotation forms an offer. Transformers & Rectifiers Ltd edits terms and conditions then sends back to supplier, this act terminates Needs's offer and makes a new offer. Delivery of goods can be deemed as acceptance from Needs Ltd. The contract is formed with its details in the edited terms and conditions.
Reference:
LO 1, AC 1.2
NEW QUESTION # 49
Which of the following statements is FALSE on contracts for the leasing of assets?
- A. The party responsible for maintenance, insurance and taxes is subject to negotiation
- B. The ownership of leased asset is transferred to the lessee at the end of the period
- C. The lessee may bear some risks of ownership, such as the liability to insure the asset
- D. In lease agreement, the possession and right of use of an asset are transferred to the lessee
Answer: B
Explanation:
A lease is a contractual arrangement calling for the lessee (user) to pay the lessor (owner) for use of an asset. Some characteristics of Leases are:
- The right to use the lessor's asset is granted in exchange for a fee called the lease payment.
- The lease payments are usually paid in installments.
- Leases may be long- or short-term.
- At its inception a lease agreement constitutes a mutually unperformed contract Though the ownership of the asset is not transferred to the lessee, some responsibilities and risks do. The lessor and lessee may negotiate on who is responsible on maintenance, insurance, etc.
Reference:
LO 1, AC 1.3
NEW QUESTION # 50
Which of the following are true statements about RFQ process? Select TWO that apply.
- A. RFQ process is not suitable for low value purchase
- B. RFQ process creates heavier administrative burdens than tendering process
- C. RFQ process requires the suppliers to submit their technical proposals
- D. Price is often the only variable in the RFQ and quotations
- E. Buying organisation should only send RFQ to pre-qualified suppliers
Answer: D,E
Explanation:
Request for quotations is often used when the only variable is price and the purchase value is under a financial threshold. This process is less formal than ITT. RFQ should be used in the following circumstances:
- Low-value, low-risk purchases
- When the specifications are sufficiently defined or the product/service is standardised
- Where the suppliers are pre-qualified
- Where there is a framework agreement which specifies the contract terms and conditions.
Reference:
LO 1, AC 1.1
NEW QUESTION # 51
Which of the following are the conditions for revocation of offer to be valid?
1. The offeree has not received the offer yet
2. Revocation of offer must be communicated with the offeree
3. Revocation of offer must be sent via email
4. Offeree has not accepted the offer yet
- A. 1 and 3 only
- B. 2 and 3 only
- C. 2 and 4 only
- D. 1 and 4 only
Answer: C
Explanation:
A revocation of offer is the withdrawal of a previous offer to engage in some sort of legally binding contract. The previous offer had to have been such that it would have immediately become legally binding if the other party had formally agreed to it.
A core ruling defining revocation of offers was established by Payne v. Cave. This case established that neither party is bound to an agreement until an offer has been made by one and formally accepted by the other.
If an offer has been made, the offering party has a right to withdraw it up to formal acceptance by the offeree. Revocation basically serves as formal, legally verifiable notice that a withdrawal was made, and it's valid so long as it is communicated to the offeree before they accept.
The case of Byrne v. Van Tienhoven supports this by establishing that the withdrawal of an offer by telegram is only valid if the telegram is received before the offer is accepted. The case of Dickinson v. Dodds further establishes that the party making the offer can communicate the revocation through a third party.
Reference:
- What Is a Revocation of Offer?
- CIPS study guide page 31
LO 1, AC 1.2
NEW QUESTION # 52
Under which of the following scenarios an RFQ is most likely to be used?
- A. Purchase of a small number of standardised products under a framework agreement
- B. Purchase of complex machinery
- C. When the buying organisation does not know the requirements in details and needs the input from suppliers
- D. Design of a unique and complex software code
Answer: A
Explanation:
The request for quotations is a procurement method that is used for small value procurements of readily available off-the-shelf goods, small value construction works, or small value services procurements. Request for quotations works best under a framework agreement This procurement method is also known as invitation to quote and shopping, and it does not require the preparation of tender documents to the same extent as open tendering, request for proposals or two-stage tendering.
Among 4 options:
- "Purchase of a small number of standardised products under a framework agreement": the products are standardised and there is a framework agreement in place, so RFQ is the best solution.
- "Purchase of complex machinery": Complex machinery is often a large purchase. Furthermore, suppliers' quality may vary. So RFQ is not suitable, instead, depending on the situation, buyer may opt ITT or RFP to purchase this type of machinery.
- "Design of a unique and complex software code": Unique and complex software is not off-the-shelf, thus RFQ is not suitable.
- "When the buying organisation does not know the requirements in details and needs the input from suppliers": When the detailed requirements are unknown, the best solution is request for proposal or developing dialogue with suppliers.
Reference:
- Request for Quotations
- CIPS study guide page 3-4
LO 1, AC 1.1
NEW QUESTION # 53
A supermarket purchases a new batch of house cleaner from new supplier. The supermarket is concerned about possible damage that the house cleaner may cause to consumers' floor. What type of insurance must they cover?
- A. Fire and explosion insurance
- B. Professional indemnity insurance
- C. Public liability insurance
- D. Product liability insurance
Answer: D
Explanation:
Product Liability Insurance is a form of general liability insurance meant to protect a business from financial and legal consequences as a result of bodily injury or property damage due to the use of the business's sold goods or products. Situations that are typically covered by Product Liability Insurance may include:
- A customer harms herself because of the faulty packaging on one of your products
- A drapery set that a customer purchased from your business was highly flammable and caught on fire, eventually damaging her entire kitchen
- A customer with a severe allergy finds trace amounts of tree nuts in your homemade gourmet muffins
- A homemade house cleaner that you sell damaged one of your customer's entire hardwood floor
- A customer becomes sick with food poisoning after eating old shellfish at your restaurant, goes to the hospital, and incurs medical costs caused by your contaminated food products
- A customer's pet becomes ill from ingesting some lining in a pet toy product that you sell In the scenario above, the supermarket is purchasing and reselling house cleaner, which can be covered by product liability insurance.
Public liability insurance is a type of business insurance that covers the cost of claims made by the public that happen in connection with the business activities.
Professional indemnity (PI) insurance is a commercial policy designed to protect business owners, freelancers and the self-employed if clients claim a service is inadequate.
Reference:
LO 3, AC 3.2
NEW QUESTION # 54
Which of the following documents are likely to have legal standing? Select TWO that apply:
- A. Requisition
- B. Estimate
- C. Request for information
- D. Quotation
- E. Tender
Answer: D,E
Explanation:
A quotation and a tender are both firm offers which have legal standing to the offeror. Tenders are more detailed than quotations and will include quality aspects as well as prices.
LO 1, AC 1.1 & AC 1.2
NEW QUESTION # 55
Which of the following regulates barriers to the provision of services between countries?
- A. ADA
- B. GATS
- C. Incoterms
- D. CISG
Answer: B
Explanation:
- The General Agreement on Trade in Services (GATS) is a treaty of the World Trade Organization (WTO) that entered into force in January 1995 as a result of the Uruguay Round negotiations. The treaty was created to extend the multilateral trading system to service sector, in the same way the General Agreement on Tariffs and Trade (GATT) provides such a system for merchandise trade.
- CISG is the Vienna Convention on Contracts for the International Sale of Goods. This is a voluntary treaty under United Nations Commission on International Trade Law (UNCITRAL). The purpose of the Vienna Convention is to set out a framework for international transactions based on a uniform approach. It establishes substantive rules that regulate the duties and obligations of both parties, including the delivery of goods, contract formation, and remedies for breach of contract.
- The Incoterms or International Commercial Terms are a series of pre-defined commercial terms published by the International Chamber of Commerce (ICC) relating to international commercial law. They are widely used in international commercial transactions or procurement processes and their use is encouraged by trade councils, courts and international lawyers. A series of three-letter trade terms related to common contractual sales practices, the Incoterms rules are intended primarily to clearly communicate the tasks, costs, and risks associated with the global or international transportation and delivery of goods. Incoterms inform sales contracts defining respective obligations, costs, and risks involved in the delivery of goods from the seller to the buyer, but they do not themselves conclude a contract, determine the price payable, currency or credit terms, govern contract law or define where title to goods transfers.
- ADA is Anti-Dumping Agreement (Implementation of Article VI of the GATT).
LO 1, AC 1.3
NEW QUESTION # 56
Which of the following regulates barriers to the trade of goods between Member States of WTO?
- A. NAFTA
- B. GATT
- C. CISG
- D. TRIPS
Answer: B
Explanation:
- The General Agreement on Tariffs and Trade (GATT) is a legal agreement between many countries, whose overall purpose was to promote international trade by reducing or eliminating trade barriers such as tariffs or quotas. According to its preamble, its purpose was the "substantial reduction of tariffs and other trade barriers and the elimination of preferences, on a reciprocal and mutually advantageous basis."
- CISG is the Vienna Convention on Contracts for the International Sale of Goods. This is a voluntary treaty under United Nations Commission on International Trade Law (UNCITRAL). The purpose of the Vienna Convention is to set out a framework for international transactions based on a uniform approach. It establishes substantive rules that regulate the duties and obligations of both parties, including the delivery of goods, contract formation, and remedies for breach of contract.
- The Agreement on Trade-Related Aspects of Intellectual Property Rights (TRIPS) is an international legal agreement between all the member nations of the World Trade Organization (WTO). It sets down minimum standards for the regulation by national governments of many forms of intellectual property (IP) as applied to nationals of other WTO member nations.
- The North American Free Trade Agreement (NAFTA; Spanish: Tratado de Libre Comercio de America del Norte, TLCAN; French: Accord de libre-echange nord-americain, ALeNA) is an agreement signed by Canada, Mexico, and the United States, creating a trilateral trade bloc in North America.
Reference:
LO 1, AC 1.3
NEW QUESTION # 57
Which of the following are reasons why a buying organisation adopts a model contract?
1. Extremely advantageous terms for buyer
2. Correct legal terminology
3. Supplier cannot make variation to the model form
4. Specific to industry
- A. 1 and 2 only
- B. 2 and 3 only
- C. 2 and 4 only
- D. 1 and 4 only
Answer: C
Explanation:
Advantages for the use of model forms of contract include:
* Helps to reduce the time and cost in contract development, particularly in detailed negotiation of terms and conditions.
* Avoids starting from the beginning each time, avoids" re-inventing the wheel" each time.
* Model contract forms may be widely accepted by both buyers and sellers across the industry or sector.
* Model contract forms are even handed and designed to be fair to both parties in the contract.
* Model contract forms include standard clauses that can be selected or deleted on an as required basis.
* Model contract form's standard clauses are more likely to contain the correct legal terminology without recourse to third party experts.
Disadvantages of this type of contract include:
* Terms may be less advantageous, than may be achieved through negotiations, particularly where there is one party who is much stronger than the other.
* The generic contract may be difficult to adapt to the specific circumstances between two parties.
* Terms may not necessarily include special clauses or requirements to cover a particular or unusual situation.
* Legal advice and input may still be required, particularly where significant variations to the norm are required.
* There may be costs associated with training staff in the detailed application of the model forms of contract.
Reference:
- D5 Sample QUESTION and answer
- CIPS study guide page 147
LO 3, AC 3.1
NEW QUESTION # 58
SFO procurement manager sent a request for quotation to Vogon International in which he determined the contract terms and specification. In SFO's standard terms and conditions, it is stated that 'Goods shall be delivered and Services performed by the applicable Delivery Date. Supplier must notify Buyer 3 days prior to the Delivery Date if Supplier is likely to be unable to meet a Delivery Date.' Vogon replied with a quotation without any amendment to SFO's terms & conditions. The SFO procurement manager found the prices were reasonable and submitted to senior management. Senior management team accepted that quotation and sent a notification to Vogon. On the Delivery Date, Vogon said they had no capacity to supply the product as the quotation due to a workers' strike. Did Vogon breach any agreement with SFO?
- A. Yes, because the contract had been formed between SFO and Vogon with the quotation as an offer and the notification as an acceptance
- B. Yes, because the contract was formed since Vogon had sent the quotation as an acceptance to SFO's offer
- C. No, because the strike is a force majeur event, so Vogon did not breach any contract with SFO
- D. No, because Vogon had no intention to be bound by the quotation, therefore, it didn't constitute a contract
Answer: A
Explanation:
SFO issued an RFQ with defined terms and condition and detailed specification. This RFQ can be considered as an invitation to treat. Vogon's quotation is an answer to the purchaser's RFQ and is an offer to SFO. The contract come to life at the time Vogon received the notification from SFO senior management.
The strike may be a force majeur event, depending on the contract particular clauses and jurisdiction. In common law countries, force majeur is applicable as an exclusion of liability only if the contract allows it. In many civil law countries, force majeur is an implied term. But in every jurisdiction, force majeur is only a reason for excluding liability for non-performance of a contract. In other words, the non-performance party is not liable for any breach if force majeur event occurs but the event does not exclude the breach.
LO 1, AC 1.2
NEW QUESTION # 59
Which of the following best defines an 'express' term in general contract arrangements?
- A. It is the term that is added to the contract by the law or based upon the facts of the case.
- B. It is a standard set of terms and conditions published by CIPS
- C. It is not necessarily discussed by the parties, but nonetheless forms part of the contract
- D. It is clearly agreed between the parties, and is virtually always written down in the contract
Answer: D
Explanation:
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties.
Implied terms are terms implied into the contract by the courts. They are not expressly set out in the contract but are taken to be as effective as if they were and as if they had been included from day one of the contract. The express terms and any implied terms together create the legally binding obligations on the parties.
Reference:
- Contracts: Express and Implied Terms
- CIPS study guide 126-132
LO 3, AC 3.1
NEW QUESTION # 60
Which of the following is an example of liquidated damages clause?
1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."
2. "If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"
3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."
4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"
- A. 1 and 2 only
- B. 1 and 3 only
- C. 3 and 4 only
- D. 2 and 4 only
Answer: A
Explanation:
Liquidated damages, also referred to as "liquidated and ascertained damages" (LADs) are damages whose amount the parties designate during the formation of a contract[2] for the injured party to collect as compensation upon a specific breach (e.g. late performance). In supply contracts and work contracts, the liquidated damages clause often take form as known damages to be paid per day delayed. Number 1 and 2 are examples of this clause.
Reference:
- Liquidated damages
- CIPS study guide 158-159
LO 3, AC 3.2
NEW QUESTION # 61
Which of the following is the most suitable model contract for car lift manufacturing?
- A. ITC
- B. FIDIC
- C. IMechE/IET
- D. CIPS
Answer: C
Explanation:
IMechE/IET: Institution of Mechanical Engineers/Institution of Engineering and Technology - two separate institutes that issue jointly agreed model forms covering the design, supply and installation of electrical, electronic and mechanical plant including special conditions for the ancillary development of software. Car lifts are mechanical products, so IMechE/IET is the most suitable model contract for this type of product.
FIDIC is a French language acronym for Federation Internationale Des Ingenieurs-Conseils, which means the international federation of consulting engineers. It was started in 1913 by the trio of France, Belgium and Switzerland. The United Kingdom joined the Federation in 1949. FIDIC is headquartered in Switzerland and now boasts of membership from over 60 different countries. FIDIC published its first contract, titled The Form of contract for works of Civil Engineering construction, in 1957. As the title indicated, this first contract was aimed at the Civil Engineering sector and it soon became known for the colour of its cover, and thus, The Red Book. It has become the tradition that FIDIC contracts are known in popular parlance by the colour of their cover. This first contract by FIDIC was undertaken jointly with the International federation of Building and Public works. FIDIC's concerted effort at achieving broad consultation and acceptance of its contract forms has seen subsequent editions of its contracts being ratified by the International Federation of Asian and Western Pacific Contractors Association, Associated General Contractors of America and the Inter-American Federation of the Construction Industry, Multilateral Development Banks among others. Because of the broad support it enjoys, FIDIC contracts are the foremost contracts in international construction.
The Chartered Institute of Procurement and Supply (CIPS) has some model contracts for IT functions including: supply and installation of computer equipment, support and maintenance of bespoke software, servicing of computer equipment,...
The International Trade Centre (ITC) produces contracts specifically designed for small companies doing international business, covering the sale of goods, distribution, services and joint ventures.
Reference:
LO 3, AC 3.1
NEW QUESTION # 62
Which of the following is set down in statute as a liability that exists without any need to prove fault?
- A. Strict liability
- B. Contingent liability
- C. Current liability
- D. Non-current liability
Answer: A
Explanation:
- Strict liability, sometimes called absolute liability, is the legal responsibility for damages, or injury, even if the person found strictly liable was not at fault or negligent. Strict liability has been applied to certain activities in tort, such as holding an employer absolutely liable for the torts of her employees, but today it is most commonly associated with defectively manufactured products. In addition, for reasons of public policy, certain activities may be conducted only if the person conducting them is willing to insure others against the harm that results from the risks the activities create.
- Current liabilities are a company's short-term financial obligations that are due within one year or within a normal operating cycle.
- Non-current liabilities, also called long-term liabilities or long-term debts, are long-term financial obligations listed on a company's balance sheet
- Contingent liability is a potential liability that may occur, depending on the outcome of an uncertain future event.
Reference:
LO 3, AC 3.2
NEW QUESTION # 63
What is the purpose of using key performance indicators in procurement and supply?
- A. To qualify which supplier is suitable
- B. To monitor supplier's performance
- C. To validate the supplier's bid or tender
- D. To ease the termination process
Answer: B
Explanation:
Procurement teams use key performance indicators (KPIs) to ensure vendors comply with (and hopefully exceed) the obligations outlined in a contract. They help us better understand suppliers' performance, measure their output over a long period of time, and identify areas where improvement is needed.
Put simply, it's good business sense to make sure you're actually getting what you've paid for. This might be as straightforward as confirming a product or service is delivered on time, which means the KPIs you need to use will be minimal and basic.
Reference:
- Supplier KPIs | 7 Performance Indicators You Should Be Measuring - Una
- CIPS study guide page 101-102
LO 2, AC 2.2
NEW QUESTION # 64
Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark's procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?
- A. Negligence
- B. Collateral warranty deed
- C. Insurance
- D. Indemnity
Answer: B
Explanation:
A Collateral Warranty is a contract under which a consultant, a building contractor or a sub- contractor warrants to a third party that is has fulfilled its obligations under its professional appointment, building contract or sub-contract. The purpose of a Collateral Warranty is to give a third party, who is not a party to the original contract, rights to enforce that original contract.
In this case, IBM is the subcontractor, then purchaser can use collateral warranty deed to bind them.
Reference:
- Collateral Warranties - an Overview
- CIPS study guide page 39-40
LO 1, AC 1.2
NEW QUESTION # 65
Which of the following is most likely to reduce ITT preparation time while maintaining the clarity of tendering documents?
- A. Using request for quotation
- B. Monitoring usage
- C. Eliminating pre-qualification stage from all tendering processes
- D. Standardising documentation whenever possible
Answer: D
Explanation:
One of the major disadvantages of tendering process is that it is lengthy, bureaucratic and slow. To reduce the preparation time, buying organisation can:
- Plan forward
- Standardise tendering documents (such as notices, terms and conditions,...) whenever possible
- Train procurement staff
- Write down policies for tender-waiver
Buying organisation should not eliminate the pre-qualification stage from all tendering processes. This stage is used as a filter to select the most competent suppliers for next stage in restricted tendering. To save time in this process, you can design a model questionnaire.
Reference:
LO 1, AC 1.1
NEW QUESTION # 66
Which of the following is regulated by standard ISO 14001?
- A. Energy management
- B. Information security management
- C. Quality management systems
- D. Environmental management
Answer: D
Explanation:
ISO has about 22,000 international standards covering a vast range of aspects of product or service quality. Below are some of the most common ISO standards:
- ISO 9001: Quality management system
- ISO 27001: Information security management
- ISO 5001: Energy management
- ISO 14001: Environmental management
Reference:
- ISO 14001:2015 Environmental management systems - Requirements with guidance for use
- CIPS study guide page 86
LO 2, AC 2.1
NEW QUESTION # 67
What does quantum meruit mean?
- A. A non-graduations promise
- B. An implied promise
- C. As much as is earned
- D. As much as is paid
Answer: C
Explanation:
Quantum meruit means "the amount he deserves" or "as much as he has earned". In most cases it denotes a claim for a reasonable sum in respect of services or goods supplied to the defendant.
An action in quantum meruit is available to recover money for services or goods supplied to a defendant in circumstances where the claimant is not recompensed by performing his obligations or supplying the goods. The claimant must usually show that the defendant expressly or impliedly requested or freely accepted the services or goods in question. Depending on the facts, the claimant might find it difficult to prove how much the claimant is entitled to receive under the principle of quantum meruit.
A claim for quantum meruit cannot arise if the parties have a contract to pay an agreed sum. In such circumstances, the parties' relationship is governed by the law of contract. However, a claim for quantum meruit may arise where the parties:
- Have not agreed a contract, or there is a so-called quasi-contract. For example, the parties may have agreed some of the contractual terms, but may have failed to reach an agreement on an essential term, such as price.
- Have not fixed a price for the services or goods supplied.
- Have an agreement to pay a reasonable sum for the services or goods supplied.
- Have agreed a scope of work under the original contract and the work carried out falls outside that scope.
Reference:
LO 3, AC 3.1
NEW QUESTION # 68
......
Use Real CIPS Achieve the L4M3 Dumps - 100% Exam Passing Guarantee: https://www.pass4leader.com/CIPS/L4M3-exam.html
Verified L4M3 Q&As - Pass Guarantee L4M3 Exam Dumps: https://drive.google.com/open?id=1hwjKV_R7ZoloDCEuZAYNx5fMBGQcSMbm