
Dec-2024 Free SAP C_S43_2023 Exam Question Practice Exams
Ace C_S43_2023 Certification with 82 Actual Questions
NEW QUESTION # 46
What happens if you change the primary key of a functional location?
- A. Changing the superior functional location via alternative labeling is not possible.
- B. The functional location cannot be assigned to a new superior functional location when the new label is entered.
- C. The user must define a new labelling system for the new primary key.
- D. The user must decide whether the functional location is assigned to a new superior functional location.
Answer: D
Explanation:
Changing the primary key of a functional location means changing the label of the functional location. The label is the unique identifier of the functional location and it consists of a structure indicator and a functional location identification. The structure indicator defines the allowed characters and the hierarchy levels of the functional location structure. The functional location identification is the actual name of the functional location. When youchange the primary key of a functional location, you can either change the structure indicator or the functional location identification, or both. If you change the structure indicator, you need to adjust the functional location identification accordingly. If you change the functional location identification, you need to decide whether the functional location is assigned to a new superior functional location or not. A superior functional location is the functional location that is directly above the current functional location in the hierarchy. For example, if you have a functional location FL-01-02-03, where FL is the structure indicator,
01 is the first level, 02 is the second level, and 03 is the third level, you can change the primary key to FL-01-
02-04, which means changing the functional location identification within the same level. In this case, you need to decide whether the functional location is still assigned to FL-01-02 as the superior functional location or not. Alternatively, you can change the primary key to FL-01-03, which means changing the functional location identification to a different level. In this case, you need to decide whether the functional location is still assigned to FL-01 as the superior functional location or not.
The user does not need to define a new labelling system for the new primary key, as the labelling system is defined by the structure indicator, which can be reused for different functional locations. Therefore, answer A is incorrect. The functional location can be assigned to a new superior functional location when the new label is entered, as long as the new label is consistent with the structure indicator and the hierarchy rules. Therefore, answer B is also incorrect. Changing the superior functional location via alternative labeling is possible, as alternative labeling allows you to assign different labels to the same functional location. Therefore, answer C is also incorrect. References: Explaining Technical Asset Structures - SAP Learning, Organizational Elements and Structures | SAP Help Portal, and SAP Alternative Labeling of Functional Locations.
NEW QUESTION # 47
What are characteristics of the structure indicator? Note: There are 2 correct answers to this question
- A. It limits the types of characters in the edit mask to Alpha and Numeric.
- B. It restricts the number of hierarchical levels to no more than 6
- C. It sets the hierarchy levels of the functional location structure.
- D. It defines the allowed characters for a functional location
Answer: C,D
Explanation:
The structure indicator is a key that defines the allowed characters and the hierarchy levels of the functional location structure. It consists of an edit mask and a hierarchy indicator. The edit mask defines the allowed characters for each position of the functional location identification. The hierarchy indicator defines the hierarchy levels of the functional location structure and the number of characters for each level. For example, a structure indicatorwith the edit mask ANNNN-NNNN and the hierarchy indicator 5-4 means that the functional location identification can have up to 9 alphanumeric characters, divided into two levels with 5 and
4 characters respectively, separated by a hyphen. The structure indicator does not limit the types of characters to alpha and numeric, as it can also include special characters, such as hyphens, slashes, or dots. Therefore, answer A is incorrect. The structure indicator also does not restrict the number of hierarchical levels to no more than 6, as it can have up to 10 levels. Therefore, answer B is also incorrect. References: Explaining Technical Asset Structures - SAP Learning and Organizational Elements and Structures | SAP Help Portal.
NEW QUESTION # 48
What are characteristics of the Preparation and Scheduling phase within phase-based maintenance?
Note: There are 2 correct answers to this question.
- A. Maintenance Planning Buckets give you a list of non-approved notifications.
- B. The configuration of the order type decides whether you use Resource Scheduling or not.
- C. The order moves to the Preparation phase once it is approved and released.
- D. If you use the Resource Scheduling apps, you always dispatch orders and operations.
Answer: C,D
Explanation:
Maintenance Processing - Advanced Functions
NEW QUESTION # 49
Which operations can the responsible person perform after a maintenance order is technically completed?
Note: There are 2 correct answers to this question
- A. Change the planned costs
- B. Change the settlement rule
- C. Lock or unlock the order
- D. Update the estimated costs
Answer: B,C
Explanation:
After a maintenance order is technically completed, the responsible person can perform the following operations1:
* Lock or unlock the order: This prevents or allows further changes to the order data, such as actual costs, settlement rule, or confirmation data.
* Change the settlement rule: This allows the responsible person to adjust the distribution of costs to the relevant receivers, such as cost centers, assets, or orders.
* Post goods movements: This allows the responsible person to record the consumption or return of materials that were used for the maintenance work.
* Enter measurement documents: This allows the responsible person to record the measurement readings of the technical objects that were maintained.
The responsible person cannot perform the following operations after a maintenance order is technically completed1:
* Update the estimated costs: This is only possible before the order is released or during the execution phase.
* Change the planned costs: This is only possible before the order is released or during the execution phase.
* Change the order type: This is only possible before the order is released.
* Change the order status: This is only possible before the order is technically completed or after it is reversed.
Therefore, the correct answers are A and C. References: 1: Maintenance Order Types | SAP Help Portal
NEW QUESTION # 50
How can you assign a material BOM to a piece of equipment?
- A. Via field model number in the equipment master
- B. Via field construction type
- C. Via material BOM header in the serialization data
- D. Via creation of an equipment BOM
Answer: B
Explanation:
A material BOM is a list of components that make up a material. It can be used to describe the structure and composition of a product or a spare part. A material BOM can be assigned to one or more technical objects, such as equipment or functional locations, to define the materials required for maintenance activities1.
One way to assign a material BOM to a piece of equipment is via the field construction type in the equipment master. The construction type is a material number that identifies the material BOM for the equipment. By entering the construction type in the equipment master, the system automatically assigns the material BOM to the equipment2.
The other options are incorrect because:
* Via field model number in the equipment master: The model number is a material number that identifies the material of the equipment itself, not the material BOM. It is used to create an equipment BOM, which is a list of components that are installed on the equipment. An equipment BOM can be different from a material BOM, as it can reflect the actual configuration of the equipment2.
* Via material BOM header in the serialization data: The serialization data is a view in the material master that contains information about the serial numbers of the material. It is not related to the material BOM or the equipment assignment3.
* Via creation of an equipment BOM: The creation of an equipment BOM is a different process from the assignment of a material BOM. An equipment BOM can be created from a material BOM, but it does not automatically assign the material BOM to the equipment. An equipment BOM can also be created manually or copied from another equipment2.
References: 1: Using Bills of Materials (BOMs) - SAP Learning 2: SAP PM Bills of Material Tutorial - Free SAP PM Training - ERProof 3: Serialization Data (SAP Library - Material Master (LO-MD-MM))
NEW QUESTION # 51
How does a maintenance request within the phase-based process differ from a maintenance notification in the standard process?
- A. It is a new business object with no connection to a maintenance notification.
- B. It contains an additional screening phase where requests can be accepted or rejected.
- C. It is mandatory to assign a task list to the maintenance request.
- D. It always uses the risk-based assessment for prioritization.
Answer: B
Explanation:
A maintenance request within the phase-based process differs from a maintenance notification in the standard process in that it contains an additional screening phase where requests can be acceptedor rejected. In the standard process, a maintenance notification is created and processed without any screening. In the phase- based process, a maintenance request is created and submitted for screening. The screening phase allows the supervisor to review the request and decide whether to accept it or reject it. If the request is accepted, it becomes a maintenance notification and moves to the planning phase. If the request is rejected, it is closed and no further action is taken1.
The other options are incorrect because:
* A maintenance request does not always use the risk-based assessment for prioritization. It can also use a predefined priority list2.
* A maintenance request is not a new business object with no connection to a maintenance notification. It is a maintenance notification that is in the initiation or screening phase3.
* It is not mandatory to assign a task list to the maintenance request. A task list can be assigned to the maintenance order in the planning phase4.
References: Explaining the Phase-based Process, New Phase Model for the Maintenance Processes in S
/4HANA Cloud, SAP S/4HANA Cloud release of 2011 - Asset Management (Maintenance Management), Introducing Reactive Maintenance (4HH)
NEW QUESTION # 52
Which functions are available in the Resource Scheduling for Maintenance Planners app?
Note: There are 2 correct answers to this question.
- A. Dispatch maintenance order operations.
- B. Print job papers from a maintenance order.
- C. Schedule and dispatch maintenance operations by shifts.
- D. Monitor maintenance order operations due in the next 4 weeks.
Answer: A,D
Explanation:
Maintenance Processing - Basic Functions
NEW QUESTION # 53
The planner adds stock materials in the maintenance order. What are possible options for handling of reservations within a maintenance order? Note: There are 2 correct answers to this question
- A. All open reservations are closed when the maintenance order is set to TECO.
- B. Open reservations can be cleared when a maintenance order operation is finally confirmed.
- C. For the combination of order type and planner group, you can decide when reservations are created
- D. Reservations are created only after a material availability check has been performed
Answer: A,B
NEW QUESTION # 54
The maintenance technician wants to document work steps for a technical object in a notification. What are the best options to be used in regard to code-based reporting? Note: There are 2 correct answers to this question?
- A. A text in the subject long text screen
- B. A task in the notification item
- C. An entry in the object list
- D. An activity in the notification header
Answer: B,D
NEW QUESTION # 55
Which functions characterize a Strategic analysis as opposed to Embedded analysis within the SAP S/4HANA core system?
Note: There are 2 correct answers to this question.
- A. SAP BusinessObjects as a part of SAP Business Warehouse (BW)
- B. Preconfigured Core Data Service (CDS) containing SQL views
- C. SAP BusinessObjects Business Intelligence for Visualization
- D. A collection of tools that are not included with core SAP S/4HANA
Answer: A,B
Explanation:
Maintenance Processing - Basic Functions
NEW QUESTION # 56
The planner adds non-stock material in a released maintenance order. What are possible options within the maintenance order? Note: There are 3 correct answers to this question?
- A. A purchase order is created automatically as soon as the order is saved.
- B. The maintenance order can be set to TECO before the invoice is created
- C. A purchase requisition can be created automatically as soon as the order is saved.
- D. A goods receipt can be posted after the maintenance order is technically completed.
- E. A purchase requisition will ALWAYS be created as soon as the order is saved.
Answer: B,C,D
Explanation:
Non-stock materials are materials that are not kept in stock, but are procured externally as required1. They can be maintained in the material master as service products (product type SERV). You can add non-stock materials to an operation or suboperation as a component. The system creates a purchase requisition and a purchase order in the same way as for non-stock materials that you procure externally1.
Among the given options, the following are possible for non-stock materials in a released maintenance order:
* A purchase requisition can be created automatically as soon as the order is saved. This is the default behavior for non-stock materials, unless you change the configuration settings2.
* The maintenance order can be set to TECO (technically completed) before the invoice is created. This is possible if you use the compatibility mode for external procurement, which allows you to technically complete the order even if there are open purchase requisitions or purchase orders2.
* A goods receipt can be posted after the maintenance order is technically completed. This is possible if you use the enhanced mode for external procurement, which allows you to post goods receipts for non- stock materials after the order is technically completed2.
The following options are not possible for non-stock materials in a released maintenance order:
* A purchase order is created automatically as soon as the order is saved. This is not possible, as the purchase order requires manual processing and approval after the purchase requisition is created2.
* A purchase requisition will ALWAYS be created as soon as the order is saved. This is not always true, as you can change the configuration settings to create the purchase requisition manually or at a later point in time2.
Therefore, the correct answers are A, B, and C. References: 1: What's New in SAP S/4HANA 2021 - SAP Online Help 2: How to Configure SAP S/4HANA Asset Maintenance Subcontracting - SAP PRESS
NEW QUESTION # 57
What are the prerequisites for serializing a piece of equipment? Note: There are 3 correct answers to this question.
- A. Maintain a serial number for an existing equipment master.
- B. Add a serialized material to the equipment serial data view.
- C. Assign a serial number profile to the equipment category.
- D. Assign a serial number profile to an additional business view for equipment category.
- E. Assign a serial number profile to the related material master.
Answer: B,C,E
Explanation:
Technical Objects
NEW QUESTION # 58
What do you have to consider when planning maintenance work that is to be carried out by an external company?
- A. For the maintenance order type, you have to assign the Enhanced Procurement Mode.
- B. If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system.
- C. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet.
- D. In the control key assigned to the order operation, the "Service" indicator must always be activated.
Answer: D
Explanation:
Maintenance Processing - Basic Functions
NEW QUESTION # 59
You are analyzing the data transfer of the cost center of a piece of equipment. What are the possible data origins? Note: There are 2 correct answers to this question
- A. The cost center of the superior equipment
- B. The individual maintenance of the cost center in the equipment master record
- C. The reference functional location of the superior functional location
- D. The cost center of the related maintenance work center
Answer: A,B
NEW QUESTION # 60
Which of the following API types does SAP recommend to use to achieve clean core integrations? Note:
There are 2 correct answers to this question.
- A. SOAP
- B. RFC
- C. IDoc
- D. OData
Answer: A,D
Explanation:
Managing Clean Core
NEW QUESTION # 61
You want to implement SAPUI5 apps in your SAP Fiori Launchpad. Which are mandatory elements? Note.
There are 2 correct answers to this question?
- A. Web Dynpro Apps
- B. Transactions
- C. Catalogs
- D. Tile Groups
Answer: C,D
Explanation:
SAPUI5 apps are web applications that use the SAPUI5 framework to create user interfaces for SAP business applications. SAPUI5 apps can be integrated into the SAP Fiori Launchpad, which is a shell that hosts SAP Fiori apps and provides them with services such as navigation, personalization, embedded support, and application configuration1.
To implement SAPUI5 apps in the SAP Fiori Launchpad, two mandatory elements are catalogs and tile groups.
* Catalogs are collections of tiles and target mappings that define the SAPUI5 apps that can be launched from the SAP Fiori Launchpad. Tiles are the entry points to the SAPUI5 apps, and target mappings define the semantic objects and actions that are used to navigate to the SAPUI5 apps. Catalogs are created and maintained by administrators in the SAP Fiori Launchpad Designer.
* Tile groups are collections of tiles that are displayed on the SAP Fiori Launchpad home page. Tile groups are created and maintained by end users or administrators in the SAP Fiori Launchpad. Tile groups allow users to organize and access the SAPUI5 apps that are relevant for their roles and tasks.
The other options are incorrect because:
* Web Dynpro Apps are web applications that use the Web Dynpro framework to create user interfaces for SAP business applications. Web Dynpro Apps are not SAPUI5 apps, and they require a different integration approach to be launched from the SAP Fiori Launchpad.
* Transactions are executable programs in the SAP system that perform specific businessfunctions, such as creating a sales order or posting a goods receipt. Transactions are not SAPUI5 apps, and they require a different integration approach to be launched from the SAP Fiori Launchpad.
References: 1: SAPUI5 - Overview - Tutorialspoint : SAP Fiori Launchpad - SAP Help Portal : Integrating Web Dynpro ABAP Applications into the SAP Fiori Launchpad - SAP Help Portal : Integrating SAP GUI for HTML (WebGUI) Applications into the SAP Fiori Launchpad - SAP Help Portal
NEW QUESTION # 62
How does a performance-based maintenance plan calculate the interval between start date and planned date?
- A. Cycle length divided by (annual performance / 365)
- B. Cycle length divided by annual performance
- C. Cycle length divided by (monthly performance x 12)
- D. Cycle length divided by ((scheduling period) x (cycle modification factor))
Answer: B
Explanation:
Topic: 4
Maintenance Processing - Advanced Functions
NEW QUESTION # 63
Which objects have been enhanced with linear data in maintenance processes? Note: There are 3 correct answers to this question
- A. Maintenance plan item
- B. Notification item
- C. Equipment task list
- D. Maintenance plan header
- E. Work order confirmation
Answer: A,B,E
Explanation:
Linear data is used to describe the location and extent of linear assets, such as pipelines, roads, or cables.
Linear data can be stored in the master data of technical objects, such as functional locations and equipment, as well as in the transactional data of maintenance processes, such as notifications, orders, and confirmations.
The objects that have been enhanced with linear data in maintenance processes are:
* Work order confirmation: You can record the processing status of a maintenance order by entering linear data in the confirmation. You can also use the linear data from the order operation or the notification item as a default value1
* Maintenance plan item: You can define inspections and maintenance tasks in linear assets by creating and managing the maintenance items in maintenance plans with linear data. You can also use the linear data from the technical object or the task list as a default value2
* Notification item: You can describe the condition of your linear asset or report a malfunction by entering linear data in the notification item. You can also use the linear data from the technical object as a default value3 References: 1: Linear Data in Maintenance Order Confirmation 2: Linear Data in Maintenance Plan Item 3:
Linear Data in Maintenance Notification Item
NEW QUESTION # 64
Which activities can the technician perform with the Report and Repair Malfunction SAPUI5 app? Note:
There are 2 correct answers to this question
- A. Release
*Print - B. Release
*Start Work - C. Schedule
*Dispatch - D. Complete
*Close Report
Answer: B,D
Explanation:
* The Report and Repair Malfunction SAPUI5 app is a Fiori app that allows the technician to easily report that a technical object has a malfunction, plan the required repair work, as well as document and confirm the maintenance work when it's done1. With this app, the technician can perform the following activities:
* C. Complete and Close Report. This is true because the technician can provide information about the malfunction and the job, confirm the job, and close the malfunction report. The technician can also attach pictures or descriptions of the damage, as well as a URL to provide further information about the technical object or the damage1.
* D. Release and Start Work. This is true because the technician can release the malfunction report and start working on the job assigned to them. The technician can also view the details of the technical object, the history of recent repair work, the required spare parts, and the work centers involved1.
* The technician cannot perform the following activities with this app:
* A. Schedule and Dispatch. This is false because these activities are performed by the planner or the dispatcher, not the technician. The planner or the dispatcher can use the Resource Scheduling app to schedule and dispatch the maintenance orders and operations2.
* B. Release and Print. This is false because the technician can only release the malfunction report, not print it. The technician can use the Repair Malfunctions - My Job List app to view the list of all work items assigned to them and their current status, but not to print them1. References
: 1: Report and Repair Malfunction 2: Resource Scheduling
NEW QUESTION # 65
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
- A. Technical completion date of the maintenance order
- B. Actual finish date of the maintenance order
- C. The date of the final confirmation
- D. Planned date of the next call, independent of maintenance order dates
Answer: A
NEW QUESTION # 66
......
SAP C_S43_2023 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
C_S43_2023 Questions PDF [2024] Use Valid New dump to Clear Exam: https://www.pass4leader.com/SAP/C_S43_2023-exam.html
PASS SAP C_S43_2023 EXAM WITH UPDATED DUMPS: https://drive.google.com/open?id=11YylSlqyYvXvd6VWnxj8dRIf_k_ZpIhd