NEW QUESTION # 38
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

  • A. 2 cranes
  • B. 1 crane
  • C. 3 cranes
  • D. 4 cranes

Answer: A


NEW QUESTION # 39
What does the narrow band at "Y" represent?

  • A. You cannot tell with the information supplied.
  • B. A rework period.
  • C. Activity inactivity.
  • D. Resource limitation period.

Answer: C


NEW QUESTION # 40
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. It is calculated using the original logic.
  • B. There is no such thing.
  • C. An out-of-sequence activity cannot resume until all predecessors are finished.
  • D. It is calculated using logic reflecting out-of-sequence progress.

Answer: A


NEW QUESTION # 41
Which of the following is NOT required when initially planning a project?

  • A. A schedule that identifies tasks required on a project.
  • B. The duration of each task.
  • C. Logical relationships between the tasks.
  • D. Resource Identification and leveling.

Answer: B


NEW QUESTION # 42
What is the remaining work duration of Active D?

  • A. 0
  • B. 4.
  • C. 3.
  • D. 8.

Answer: B


NEW QUESTION # 43
Budgeted cost of work scheduled is _______________________.

  • A. The total authorized budget for accomplishing the project scope
  • B. The expected total cost of an activity, group of activities or the project
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The sum of all budgets for work scheduled to be accomplished within a given time period

Answer: B


NEW QUESTION # 44
These are the activities on the critical path:

  • A. A, B, F, & J
  • B. A, D, & I.
  • C. A, B, G, & H.
  • D. A, C, E, & H.

Answer: C


NEW QUESTION # 45
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

  • A. 12-18-03 and 25 days of float
  • B. 12-17-03 and 4 days of float
  • C. 12-18-03 and 4 days of float
  • D. 12-27-03 and 24 days of float

Answer: B


NEW QUESTION # 46
Constraints control events or activities that __________________.

  • A. Are not based on project relationships.
  • B. Affect only the backward pass.
  • C. May be over-ridden by activity logic.
  • D. Affect only the forward pass.

Answer: C


NEW QUESTION # 47
Project schedules help control all of the following EXCEPT for_____________________.

  • A. Quality
  • B. Time
  • C. Resources
  • D. Cost

Answer: A


NEW QUESTION # 48
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 36.
  • B. 37.
  • C. 42.
  • D. 40.

Answer: A


NEW QUESTION # 49
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Remaining duration of activities.
  • B. Percent complete.
  • C. Actual finish of activities.
  • D. Original duration of activities.

Answer: A


NEW QUESTION # 50
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

  • A. Budget at completion (BAC)
  • B. Estimate at completion (EAC)
  • C. Budgeted cost of work performed (BCWP)
  • D. Estimate to complete (ETC)

Answer: D


NEW QUESTION # 51
Activity C is a

  • A. Continuous activity.
  • B. Contentious activity.
  • C. 1-day activity.
  • D. Milestone.

Answer: D


NEW QUESTION # 52
What is a key first step in developing a critical path method schedule?

  • A. Drawing a bar chart of the key phrases of the work.
  • B. Setting out the resource to be used and its limitations.
  • C. Drawing the logic diagram.
  • D. Defining the execution plan to meet the required scope of work.

Answer: C


NEW QUESTION # 53
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Planning and design phase.
  • B. Claims and disputes phase.
  • C. Turnover and start-up phase.
  • D. Installation phase.

Answer: A


NEW QUESTION # 54
What method offers the best chance of the schedule being used effectively to implement the project in the field?

  • A. Include detailed and stringent set of scheduling specifications in the contract.
  • B. Obtain consent and agreement to the schedule from the key project personnel.
  • C. Allow large time contingencies on milestones and completion deadlines.
  • D. Issue detailed schedule updates as frequently as possible.

Answer: B


NEW QUESTION # 55
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

  • A. ADM uses arrows, while PDM uses boxes.
  • B. ADM is limited to finish-to-start logic relationships, while PDM is not.
  • C. PDM is a bar chart with network logic, while ADM is a pure logic network.
  • D. ADM is manual CPM calculations, while PDM is computerized.

Answer: B


NEW QUESTION # 56
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

  • A. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • B. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • C. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

Answer: A


NEW QUESTION # 57
What is the workweek period for this project?

  • A. Monday through Friday
  • B. Sunday through Friday
  • C. Sunday through Saturday
  • D. Monday through Saturday

Answer: C


NEW QUESTION # 58
......