You want to create a production order from a planned order. What methods could you use?
Correct Answer: A,B
Vote an answer
For a production version to be valid and consistent what requirements must be fulfilled?
Correct Answer: A,B,C
Vote an answer
What is the purpose of a reporting point confirmation in repetitive manufacturing?
Correct Answer: A,B
Vote an answer
In your plant, MRP is activated.
Which option do you have to exclude a materila from the MRP run?
Which option do you have to exclude a materila from the MRP run?
Correct Answer: A,D
Vote an answer
Where do you maintain data to determine the duration of an operation for production?
Correct Answer: C,D
Vote an answer
Your quality department detect a deviation in a raw material batch. Unfortunately, this batch has already been used in producion. How can you indentify all affected finish goods stocks?
Correct Answer: C
Vote an answer
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Correct Answer: A,B,E
Vote an answer
Which of the following elements does MRP take into account during net requirement calculation?
Correct Answer: A,C
Vote an answer
What are the consequences if the Dispatched operation status is set for a production order operation?
Correct Answer: A,B