A company's marketing department fails an internal compliance audit. To comply with the auditor's remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
Correct Answer: D Vote an answer
Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?
Correct Answer: D Vote an answer
What type of contract provides the buyer with the most risk and seller the least risk?
Correct Answer: C Vote an answer
You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?
Correct Answer: C Vote an answer
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase.
Tracking and reporting of actual benefits realized is one part of the review.
What is the other part of the review?
Correct Answer: A Vote an answer
Which project management meeting allows stakeholders to meet one another and to learn about the project?
Correct Answer: C Vote an answer
After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?
Correct Answer: B Vote an answer
You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?
Correct Answer: D Vote an answer
Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?
Correct Answer: D Vote an answer
Which of the following risk identification techniques is described in the statement below?
"It is used to gather information where participants don't know each other nor do they have to be present at the same location."
Correct Answer: D Vote an answer
A complex technology program consisting of nine projects is at risk of delayed deliverables. A team member found a valid alternative solution that allows parallel implementation of three components previously planned to be implemented sequentially. Which document should the program manager update?
Correct Answer: C Vote an answer