Free NABCEP PVIP Practice Test & Real Exam Questions
A customer has a 200A service with a 200A rated panel and 200A main breaker located on the street side of the house. There is a 100A breaker located at the opposite end of busbar feeding a 125A subpanel in the backyard. The customer would like to place the inverter the backyard and use the 125 subpanel. Which MAXIMUM inverter(s) output circuit current could be installed?
Correct Answer: D
Vote an answer
A 20 kW array has a measured output of 16 kW at 800 W/m² irradiance. What is the performance loss due to irradiance?
Correct Answer: B
Vote an answer
A homeowner is concerned that a 6kWdc PV system might be experiencing a performance issue. The homeowner has noticed what appears to be declining production. The installer analyzes the following data acquisition system (DAS) results for each year since the installation:

Given the data, which is the MOST likely conclusion to draw?

Given the data, which is the MOST likely conclusion to draw?
Correct Answer: B
Vote an answer
A PV module has a temperature coefficient of power of -0.4%/°C and a rated power of 300W at STC (25°C).
What is the expected power output if the module temperature rises to 55°C?
What is the expected power output if the module temperature rises to 55°C?
Correct Answer: B
Vote an answer
A PV system was installed in July 2017 under the 2017 NEC. The system has a string inverter located inside a garage on a wall 10 ft, from the outside wall and 1oft, from the ac load center at the point of utility connection. The PV system has a PV array on the roof. Which of the following represents the PV rapid shutdown system requirement for the controlled PV system conductors associated with this PV array?
Correct Answer: B
Vote an answer
Which of the following voltages should be included on the dc disconnected label to indicate MAXIMUM system voltage?
Correct Answer: C
Vote an answer
A PV system is installed on a dwelling with a single-phase 240V service. The inverter output is 7.2 kW. What is the minimum service conductor size per NEC 705.12 if the existing load is 50A?
Correct Answer: A
Vote an answer
A bank of batteries with capability of supplying 250A and a maximum voltage of 325V is housed in a concrete structure in a very humid location. There is service access alsie between rows of batteries. What is the REQUIRED safety distance between the rows of batteries.
Correct Answer: B
Vote an answer
A ground-mount array uses driven piles with a lateral load capacity of 500 lbs. The wind load calculation yields a lateral force of 600 lbs per pile. What must be done?
Correct Answer: A
Vote an answer
A maintenance inspection reveals cracked module glass. What is the immediate action?
Correct Answer: D
Vote an answer
A 12 kW array has a measured output of 10 kW at STC due to mismatch losses. What is the mismatch loss percentage?
Correct Answer: B
Vote an answer
A rooftop PV system is proposed for a commercial building with a membrane roof. The structural engineer specifies a maximum allowable dead load of 5 psf. The PV modules weigh 3 psf, and the racking adds 1.5 psf.
What additional load can be added without exceeding the limit?
What additional load can be added without exceeding the limit?
Correct Answer: D
Vote an answer
A PV array with 58 in. X 38 in modules in portrait orientation is to be mounted at a 35 tiit angle on a shingle roof that has a 5:12 pitch. Assuming the support leg is attached to the top of the modules and is perpendicular to its face, what is the length of the support leg for the modules?


Correct Answer: A
Vote an answer
A ground resistance measurement on a newly installed grounding electrode indicates a resistance of 130#. The earth connection may be improved by connecting the existing electrode to a:
Correct Answer: B
Vote an answer