About Huawei SUN2000L household inverter installation space requirements, which of the following description is correct? (Multiple choice)
Correct Answer: A,C,D Vote an answer
In the requirements for safe construction work, which of the requirements for on-site management are correct?
Correct Answer: A Vote an answer
When Huawei SmartLogger "Device Auto Access" is set to "Enable", SmartLogger will automatically search for devices every 10 minutes and automatically access new devices.
Correct Answer: B Vote an answer
Which of the following description about the operation of the software are correct? (Multiple choice)
Correct Answer: A,B,C,D Vote an answer
Huawei intelligent photovoltaic power plant monitoring and management system can achieve centralized and mobile operation and maintenance.
Correct Answer: B Vote an answer
The following description belongs to the characteristics of the fiber ring network (). (Multiple Choice)
Correct Answer: A,B,D Vote an answer
The following documents belonging to the output document in the project supervision process are (). (Multiple Choice)
Correct Answer: A,B,C Vote an answer
When the debugging of the Huawei PLC communication network is started, which of the operation description of setting the anti-crosstalk is correct? (Multiple Choice)
Correct Answer: A,B,C,D Vote an answer
The rated output current of Huawei PID module is ____.
Correct Answer: A Vote an answer
Huawei SUN2000 inverter has no fuses and no internal fan for easy maintenance and improved service life.
Correct Answer: A Vote an answer
Huawei intelligent photovoltaic power plant monitoring and management system includes (). (Multiple Choice)
Correct Answer: B,C,D Vote an answer
Huawei SUN2000 inverter mode switching, which is wrong?
Correct Answer: D Vote an answer
Low Voltage Ride Through (LVRT) means that when a power system accident or disturbance causes a voltage drop at the grid connection point of a PV power plant, the PV power plant can ensure continuous operation without off-grid.
Correct Answer: A Vote an answer
The PID effect refers to the phenomenon of ion migration caused by the high voltage of the photovoltaic module between the cell and its grounded metal frame, which causes the performance degradation of the component.
Correct Answer: B Vote an answer