Which of the following is not reflected in a Sprint Burn down Chart?
Correct Answer: D
Vote an answer
Development Team members volunteer to own a Sprint Backlog item:
Os membros da equipe de desenvolvimento voluntario de possuir um item do Sprint Backlog:
Os membros da equipe de desenvolvimento voluntario de possuir um item do Sprint Backlog:
Correct Answer: C
Vote an answer
Under what circumstances should separate Product Backlogs be maintained?
Correct Answer: D
Vote an answer
Andrea is a very productive team member, but she's always poking around for information and asking for details, especially in areas of the project that she isn't involved in. What should you do?
Correct Answer: C
Vote an answer
Who determines whether the development team has been assigned enough work in a Sprint?
Correct Answer: B
Vote an answer
True or False: The Scrum Framework encompasses rules or guidelines for architecture?
Correct Answer: A
Vote an answer
A _____________________ is created during the first half of the Sprint planning meeting and a
_________________ is created during the second half of the Sprint planning meeting?
_________________ is created during the second half of the Sprint planning meeting?
Correct Answer: A
Vote an answer
True or False: Scrum Team is self-empowered to do whatever is necessary to achieve sprint goal within organization guidelines.
Correct Answer: B
Vote an answer
Which system provides evolutionary framework for incremental process improvement?
Correct Answer: A
Vote an answer
Which of the following is not a Scrum Master responsibility?
Correct Answer: D