Free SAP C_TS412_1909 Practice Test & Real Exam Questions
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
What do you have to consider?
Correct Answer: A
Vote an answer
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
Correct Answer: C
Vote an answer
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
Correct Answer: C,D
Vote an answer
How are earliest dates and latest dates of activities scheduled?
Correct Answer: C
Vote an answer
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
Correct Answer: A,B
Vote an answer
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
Correct Answer: B,D
Vote an answer
You have created an internally-processed network activity, and assigned a work center and the work. After saving,
you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
Correct Answer: A,B,D
Vote an answer