With reference to WBS scheduling, which of the following statements are FALSE?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Vote an answer
How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully responsible for procurement?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Vote an answer
What is the flag used for WBS elements for which you want to plan costs?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
Which scenario does not allow you to access the project team of the higher-level WBS element during
"workforce planning"?
Please choose the correct answer.
Response:
"workforce planning"?
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
In which of the following levels can you execute BOM transfer in the order browser?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Vote an answer
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer
Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What is the prerequisite for scheduling of events? *
Correct Answer: B
Vote an answer
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data?
Please choose the correct the answer.
Response:
Please choose the correct the answer.
Response:
Correct Answer: A
Vote an answer
Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project.
Which of the following can be assigned?
There are 3 correct answers to this question.
Response:
Which of the following can be assigned?
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Vote an answer
Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer
You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS).
However, once you enter the WBS element and the working hours in CATS you receive an error message.
What could be the reason?
Please choose the correct answer.
Response:
However, once you enter the WBS element and the working hours in CATS you receive an error message.
What could be the reason?
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer
Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Vote an answer