In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
Correct Answer: B,C,D
Vote an answer
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default.
However, some materials need to have a different planning horizon.
Which procedure do you recommend for setting the planning horizon?
However, some materials need to have a different planning horizon.
Which procedure do you recommend for setting the planning horizon?
Correct Answer: C
Vote an answer
What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)
Correct Answer: A,C,E
Vote an answer
During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system.
Which of the following procurement type properties are valid? (Choose two)
Which of the following procurement type properties are valid? (Choose two)
Correct Answer: B,C
Vote an answer
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
Correct Answer: A
Vote an answer
The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?
Correct Answer: C
Vote an answer
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define? (Choose two)
What does a firming type define? (Choose two)
Correct Answer: A,C
Vote an answer
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?
What do you have to consider in this scenario?
Correct Answer: A
Vote an answer
What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
Correct Answer: B,C