Which of the following documents form part of a FIDIC Construction Contract [ " Red Book " (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Correct Answer: C,D
Vote an answer
The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?
Choose all of the correct answers (multiple possibilities).
Choose all of the correct answers (multiple possibilities).
Correct Answer: A,C
Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
Correct Answer: A
Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Choose all of the correct answers (multiple possibilities).)
Correct Answer: B,D
Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor ' s Proposal. Which two of the following statements are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).
Choose all of the correct answers (multiple possibilities).
Correct Answer: B,D
Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
(What is the maximum period for the Engineer to issue the Notice of Commencement Date?)
Correct Answer: B
Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?
Choose all of the correct answers (multiple possibilities)
Choose all of the correct answers (multiple possibilities)
Correct Answer: A,D
Vote an answer