A customer is performing backups of their desktop/laptop clients to an Avamar server. They
plan to add a secure Oracle database server as a new backup client. They are concerned about the security of the database data since no data is being encrypted when it is stored on the Avamar.
What is a consideration of enabling encryption at rest?
Correct Answer: C Vote an answer
A customer wants an EMC Avamar solution that provides 8 TB of deduplicated data protection. In addition, they need to protect a VNX system and export data to tape. They anticipate data growth of another 6 TB in the next year.
Which Avamar components should be used to architect the solution, in as few nodes as possible, while meeting sizing best practices?
Correct Answer: D Vote an answer
Scnario 2:
A customer is currently using third-party backup software for Oracle backups and writing backups to third-party physical tape libraries and a VTL. Backups sent to the VTL are then vaulted to tape and transported daily from the primary data center to the third-party facility.
They are experiencing high backup job failures with backup success rates of approximately 65%. In addition, their time to disaster recovery readiness for backups is greater than 24 hours. The retention period for database backups from disk-based backup is 4 weeks.
The customer is looking for a solution that will meet the following requirements:
Oracle DBA to manage backups through Oracle RMAN Backup their file system data using EMC backup software Perform monthly full backups directly to physical tapes for offsite storage Reduce the backup window to the possible maximum Increase the time to disaster recovery readiness. Increase the retention period for database backups from disk-based backup to 6 weeks No additional WAN bandwidth requirements Low TCO solution Free up the Fiber Channel switch infrastructure Increase operational efficiency
Refer to Scenario .
Which EMC solution will meet the customer's requirements?
Correct Answer: D Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
A customer is considering implementing an EMC Disk Library with Active Engine Failover (AEF). Front-end ports 1, 3, and 4 from Engine A will be connected to the SAN. On Engine B, front-end ports 7, 8, and 11 will be connected to the SAN.
To ensure proper AEF functionality, what is the total number of front-end ports from both engines that need to be connected to the SAN?
Correct Answer: A Vote an answer
An EMC Avamar customer has added a new file system client to their moderately full Avamar single-node server.
The single-node server is running in steady state and the initial backup is complete.
What is the estimated time to backup this file server of 3 million files each night?
Correct Answer: C Vote an answer
Scenario
A customer is currently using third-party backup software for Oracle backups and writing backups to third-party physical tape libraries and a VTL. Backups sent to the VTL are then vaulted to tape and transported daily from the primary data center to the third-party facility.
They are experiencing high backup job failures with backup success rates of approximately 65%. In addition, their time to disaster recovery readiness for backups is greater than 24 hours. The retention period for database backups from disk-based backup is 4 weeks.
The customer is looking for a solution that will meet the following requirements:
Oracle DBA to manage backups through Oracle RMAN Backup their file system data using EMC backup software Perform monthly full backups directly to physical tapes for offsite storage Reduce the backup window to the possible maximum Increase the time to disaster recovery readiness. Increase the retention period for database backups from disk-based backup to 6 weeks No additional WAN bandwidth requirements Low TCO solution Free up the Fiber Channel switch infrastructure Increase operational efficiency
Refer to Scenario .
The customer is considering using an EMC Data Domain system. They would like to have a copy of the Oracle RMAN backups at their primary and disaster recovery sites.
Which Data Domain licenses are required for this solution while meeting the customer's requirements?
Correct Answer: A Vote an answer
Explanation: Only visible for Pass4Leader members. You can sign-up / login (it's free).
You aredesigning a backup solution for an EMC NetWorker customer. Based on EMC best practices, how many CPU cycles are needed by tie storage node when backing up clients over the network to local tape drives at a rate of 100 MB/s?
Correct Answer: D Vote an answer
A customer wants to change their backup and recovery strategy for their VMware Windows environment. They do not need to use encryption for the backup of the virtual machines. The customer plans to implement Avamar full image backups. Over 80% of restore requests are for single files. As a result of the restore, which item is unavailable?
Correct Answer: B Vote an answer
An EMC NetWorker customer uses AFTDs connected to a Data Domain CIFS share.
They want to configure clone controlled replication within NetWorker from one Data Domain to another.
Which Data Domain license is necessary to meet the customer's criteria?
Correct Answer: A Vote an answer
An EMC NetWorker customer is considering implementing deduplication into their existing environment. Which design consideration has the most positive impact on the deduplication ratio?
Correct Answer: C Vote an answer
The EMC account team has been asked to design a new EMC NetWorker backup solution for Microsoft Exchange Server 2007. The customer's environment consists of Microsoft Exchange Server 2007 hosted on an EMC CLARiiON disk array with EMC VSS Provider and an EMC Disk Library.
Your design needs to include a server-less backup solution for the Microsoft Exchange Server 2007 environment by leveraging the Microsoft VSS framework. What is a recommended approach to meet the customer's requirements?
Correct Answer: D Vote an answer
An existing EMC customer notices that garbage collection is not running in Avamar because the capacity limit has reached. At which capacity limit does garbage collection stop running?
Correct Answer: A Vote an answer
A customer has an operational EMC NetWorker environment using an Avamar deduplication node. They want to protect the Avamar deduplication node using replication. The customer has approached EMC for advice on what considerations they should take into account.
What is a consideration in this environment?
Correct Answer: C Vote an answer