An ___________ must determine if permanent erosion control (trench breakers) are required.
Correct Answer: B Vote an answer
List Attached C, drawing illustration Guidelines found in INGAA Foundation
Correct Answer: C Vote an answer
Orange
Correct Answer: C Vote an answer
Who is responsible for all safe work on the worksite?
Correct Answer: D Vote an answer
Install temporary slope breakers on all disturbed areas, as necessary to avoid excessive erosion. Temporary slope breakers must be installed on slopes greater than ___________percent where the base of the slope is less than ______ feet from waterbody, wetland, and road crossings at the following spacing (closer spacing shall be used if necessary
Correct Answer: A Vote an answer
Per INGAA guidelines, what is the excavation tolerance zone distance?
Correct Answer: B Vote an answer
Perform these before any mechanical ground disturbance
Correct Answer: D Vote an answer
Flattening, sloping or other excavation to modify the terrain to make it safe and accessible for construction.
Correct Answer: D Vote an answer
Inspections of excavation she,ll be conducted by competent person
a) Prior to the start of work
b) prior to the start of work and as needed throughout the shift and after every rainstorm that has an excess of 1 inch of rainfall or hazard increasing occurrence c) prior to the start of work and as needed throughout the shift and after every rainstorm that has in accidents of .5 inch of rain full or hazard increasing occurrence d) prior to the start of work and as needed throughout the shift and after every frame storm or hazard increasing occurrence
Correct Answer: A Vote an answer